Scroll Top

Wadi Al Buhair Roads & Infrastructure Works, Stage 1 – Grading and Storm Water Main Works

Wadi Al Buhair Roads & Infrastructure Works, Stage 1 – Grading and Storm Water Main Works

SKD Group has completed the roads and infrastructure works at Wadi Al Buhair which included initially, diverting the existing traffic. Then, excavation, filling and land leveling. Micro tunneling then, storm water pipe laying was done. The next step is to construct the manholes and shafts. Construction of cut of drains, construction of retaining walls, construction of retention pond and lastly, reinstatement of the existing road. Then, constructing headwalls and wingwalls at both ends of the culvert and finally, scour protection was constructed on both sides of the culvert.